supplementary heat for all heat pump installations in areas where
the temperature drops below 45° F. It is also a good practice to
provide sufficient supplementary heat to handle the entire heating
requirement should there be a component failure of the heat pump,
such as a compressor, or refrigerant leak, etc.
Since the temperature of the refrigerant in the outdoor coil on the
heating cycle is generally below freezing point, frost forms on the
surfaces of the outdoor coil under certain weather conditions of
temperature and relative humidity. Therefore, it is necessary to
reverse the flow of the refrigerant to provide hot gas in the outdoor
coil to melt the frost accumulation. This is accomplished by re-
versing the heat pump to the cooling cycle. At the same time, the
outdoor fan stops to hasten the temperature rise of the outdoor
coil and lessen the time required for defrosting. The indoor blower
continues to run and the supplementary heaters are energized.
DEFROST C ONTROL
During operation the power to the circuit board is controlled by a
temperature sensor, which is clamped to a feeder tube entering
the outdoor coil. Defrost timing periods of 30,60 and 90 minutes
may be selected by setting the circuit board jumper to 30, 60 and
90 respectively. Accumulation of time for the timing period selected
starts when the sensor closes (approximately 31° F), and when
the wall thermostat calls for heat. At the end of the timing period,
the unit’s defrost cycle will be initiated provided the sensor re-
mains closed. When the sensor opens (approximately 75° F), the
defrost cycle is terminated and the timing period is reset. If the
defrost cycle is not terminated due to the sensor temperature, a
twelve minute override interrupts the unit’s defrost period.
SUGGESTED FIELD TESTING/TROUBLE SHOOTING
1. Run unit in the heating mode (room thermostat calling for
heat).
2. Check unit for proper charge. Note: Bands of frost on the
condenser coil indicate low refrigerant charge.
3. Shut off power to unit.
4. Disconnect outdoor fan by removing the outdoor fan motor
wire from “DF2” on defrost control.
5. Restart unit and allow frost to accumulate.
6. After a few minutes of operation, the unit’s defrost
thermostat should close. To verify this, check for 24 volts
between “DFT” and “C” on board. If the temperature at the
thermostat is less than 28° F and the thermostat is open,
replace the unit’s defrost thermostat, as it is defective.
7. When the unit’s defrost thermostat has closed, short the
test pins on the defrost board until the reversing valve
shifts, indicating defrost. This should take up to 21
seconds depending on what timing period the control is
set on. After defrost initiation, the short must instantly be
removed or the unit’s defrost period will only last 2.3
seconds.
8. The control is shipped from the factory with the compressor
delay option selected. This will de-energize the
compressor contactor for 30 seconds on defrost initiation
and defrost termination. If the jumper is set to Normal, the
compressor will continue to run during defrost initiation
and defrost termination. The control will also ignore the
low pressure switch connected to R-PS1 and PS2 for 5
minutes upon defrost initiation and 5 minutes after defrost
termination.
9. After the unit’s defrost thermostat has terminated, check
the defrost thermostat for 24 volts between “DFT” and “C”.
The reading should indicate 0 volts (open sensor).
10.Shut off power to unit.
11. Replace outdoor fan motor lead to terminal “DF2” on defrost
board and turn on power.
AIRFLOW M EASUREMENT AND A DJUSTMENT
After reviewing Duct Work section, proceed with airflow measure-
ments and adjustments. The unit blower curves (see Specifica-
tion Sheets) are based on external static pressure (ESP per in/wc).
The duct openings on the unit are considered internal static pres-
sure. As long as ESP is maintained, the unit will deliver the proper
air up to the maximum static pressure listed for the CFM required
by the application (i.e. home, building, etc.)
In general, 400 CFM per ton of cooling capacity is a rule of thumb.
Some applications depending on the sensible and latent capacity
requirements may need only 350 CFM or up to 425 CFM per ton.
Check condition space load requirements (from load calculations)
and equipment expanded ratings data to match CFM and capacity.
After unit is set and duct work completed, verify the ESP with a
1-inch inclined manometer with pitot tubes or a Magnahelic gauge
and confirm CFM to blower curves in the Specification Sheets. All
units have three-speed blower motors. If low speed is not utilized,
the speed tap can be changed to medium or high speed.
NOTE: Never run CFM below 350 CFM per ton, evaporator freezing
or poor unit performance is possible.